September 2025
North Island

Lime Kiln Feed End Shell & Tyre Replacement

To successfully deliver a critical-path project involving the replacement of a section of Lime Kiln #1

Rotary Lime Kiln Replacement – Pulp & Paper Mill Annual Shutdown – September 2025

MEL worked collaboratively with OJI Fibre Solutions Engineering over a 10–12-month period to successfully deliver a critical-path project involving the replacement of a 40 tonne, 13.5-metre-long, 2.4-metre-diameter section of a lime kiln.

The project was necessary to replace the failing feed end tyre, chain system and feed flights, which were identified as high risk for both plant operation and maintenance.

This high-stakes operation was completed within a 19 ½ day (kiln burner off to burner on) schedule compared to a budgeted period of 25 days. A notable improvement in the performance of the kiln particularly with the temperature profile in the feed end of the kiln has been achieved.

Project Highlights:

  • Complex Removal in Restricted Space
    The kiln section was located within a building structure that placed restrictions on using standard lifting equipment. MEL worked with Rotary Kiln Services (RKS) and OjiFS to develop a strategy to replace the section of kiln where clearances were minimal. MEL modelled the intricate sequence of movements and to enable a temporary structure complete with rigging to be designed.

 

  • Project Management
    MEL coordinated key aspects of the project:

    • Client, Vendor and Contractor liaison.
    • Scope and Cost Estimate development.
    • Scheduling – Engineering and Construction
    • Site Construction Management.

 

  • Cost-Efficient Engineering
    To reduce costs, MEL incorporated available on-site steel and reinforced concrete load test slabs into the temporary support structures — a practical and sustainable design solution.

 

  • Construction Management
    MEL provided exemplary construction management services to deliver pre-shut, shut and post-shut services.  During the construction phase, alternative options were continually offered to fine tune the construction process without compromising the design.

 

This project showcases MEL’s ability to collaborate with the Client, Engineering Consultants, Equipment Vendors and Contractors to solve complex engineering challenges, manage on-site construction to deliver a project under pressure.